The Office Leasing Process
Time frame and tenant representative job description
1.
Define basic space requirements:
Size and layout
Expansion and option space
Price and term
Image and quality
Geographical area
Intangibles and goals
1 day
2.
Selection / interview with support team:
Space Planner
Interior Design (if desired)
Attorney / CPA
1 to 7 days
3.
Determine alternatives available:
General market knowledge of "deals" available
Search of database
Verification of terms and conditions
Review list with client
7 to 14 days
4.
Narrow down alternatives:
Inspection tours with client of likely alternatives
Selection of 3 - 5 best alternatives
Space planning of best alternatives
Review and re-draw of space plans
Selection of top 2 - 3 alternatives
Request for proposals on top alternatives
7 to 14 days
5.
Analysis of proposals and alternatives:
Financial analysis
Layout efficiencies
Intangibles and goal analysis
1 to 7 days
6.
Final selection:
Choose top alternative with client
Establish terms required
Prepare and present counter-offer
Approve, re-negotiate, or select other alternative
Review lease for business points
Review lease for legal points
Review Workletter
Re-negotiate lease terms
Sign lease
7 to 30 days
7.
Tenant improvement build-out:
Monitor progress
Report progress
Final walk through check
30 to 120 days
MINIMUM TIME ESTIMATES
Before Tenant Improvements
24 to 103 days
Including Tenant Improvements
54 to 194 days